1、 Basic conditions of the site
Requirements for Factory Space
Adequate space needs to be reserved in the installation area. Generally, the height of the factory building is not less than 8 meters, the width is not less than 10 meters, and the length depends on the equipment model (usually 20-30 meters)
At least 1.5 meters of maintenance access should be reserved around the equipment
Consider the reasonable layout of raw material storage areas, finished product storage areas, and auxiliary equipment (such as air compressors, chillers, etc.)
Ground bearing capacity and flatness
The ground bearing capacity needs to reach 5 tons/square meter or more
The ground flatness error shall not exceed ± 3mm/2m
It is recommended to use a concrete floor with a thickness of not less than 200mm and to do a good job in dust prevention
environmental conditions
Temperature control within the range of 15-35 ℃
Maintain relative humidity between 30% -70%
Avoid direct sunlight and strong airflow interference
The factory building needs to have a good ventilation system
2、 Power supply conditions
Power requirements
Voltage: 380V ± 10% (three-phase five wire system)
Frequency: 50Hz ± 2%
The total power depends on the equipment model, and generally requires a reserved power capacity of 200-500kW
An independent distribution cabinet and overload protection device are required
grounding system
Grounding resistance ≤ 4 Ω
Using a dedicated grounding wire with a cross-sectional area of not less than 16mm ²
All electrical equipment enclosures must be reliably grounded
backup power supply
Suggest configuring UPS uninterruptible power supply or emergency power generation equipment
Ensure safe shutdown of equipment in case of sudden power outage
3、 Auxiliary facility conditions
Compressed air system
Pressure requirement: 0.6-0.8MPa
Flow rate: ≥ 1.5m ³/min
Oil water separator and air drying device are required
The pipeline is made of stainless steel or galvanized material, with a diameter of ≥ 1 inch
cooling water system
Water temperature: 15-25 ℃ (not exceeding 30 ℃ in summer)
Water pressure: 0.3-0.5MPa
Flow rate: determined by equipment model, generally 10-30m ³/h
Water quality requirements: pH value 6.5-8.5, hardness ≤ 100mg/L
Suggest equipping a cooling tower or chiller unit
Raw material processing system
Raw material dryer (dew point ≤ -40 ℃) is required
Raw material conveying system (vacuum feeding or spiral conveying)
Raw material storage warehouse (moisture-proof, dust-proof)
4、 Installation technical requirements
Equipment positioning and leveling
Using laser level for equipment positioning
Levelness error ≤ 0.1mm/m
The deviation of the centerline of each unit is ≤ 1mm
Key points of mechanical installation
The extruder base is fixed using chemical anchor bolts or expansion bolts
The installation of the mold head must ensure concentricity, with a deviation of ≤ 0.05mm
Adjust the distance between the wind ring and the mold head to a better position
The traction device is synchronized with the winding device
pipeline connection
The hydraulic oil pipe adopts high-pressure hose, and a leak proof device is installed at the joint
The cooling water pipe adopts stainless steel corrugated pipe
All pipelines must indicate the flow direction of the medium
5、 Safety and environmental conditions
Safety protection facilities
Set up protective barriers and warning signs in high-temperature areas
Install protective covers on rotating components
The emergency stop button is installed in a convenient location for operation
Equip with fire extinguishing equipment (dry powder or carbon dioxide fire extinguishers)
environmental requirements
Exhaust gas collection and treatment system (activated carbon adsorption or catalytic combustion)
Noise control measures (equipment shock absorption, soundproof walls)
Waste recycling device
6、 Personnel and Technical Conditions
Installation team requirements
Installation requires guidance from professional technicians from the equipment manufacturer
Electricians, fitters, etc. need to hold certificates to work
The installation personnel are familiar with the equipment structure and working principle
Technical document preparation
Equipment installation drawings and process flow diagrams
Electrical wiring diagram and hydraulic schematic diagram
Equipment Operation and Maintenance Manual
7、 Acceptance and commissioning conditions
Post-installation check
Inspection of fastening of mechanical components
Electrical circuit insulation test (≥ 1M Ω)
Hydraulic system pressure test (1.5 times working pressure)
Debugging preparation
Prepare raw materials for debugging (it is recommended to use brand new materials)
Calibrate various temperature control systems and pressure sensors
Check the functionality of each safety interlock device
trial run
Operating without load for 4-8 hours
Gradually raise the temperature to the working temperature
Observe the operational status and parameter stability of each component
The installation of a three-layer co extrusion blown film machine is a systematic project that requires comprehensive consideration of mechanical, electrical, and process factors. Only by strictly meeting the above installation conditions can we ensure stable operation of the equipment after production and produce high-quality film products. It is recommended to keep detailed records during the installation process to provide a basis for subsequent maintenance and upkeep.